Facilities Bond & Construction Updates
   Washingtonville Central School District
  Facilities Bond 
 

 
Thank you for your support. Proposition passed 366 Yes and 293 No. 
Construction Updates
This page will be updated periodically in order to keep the public informed.
 
October 11, 2016 
·   Architectural plans, sequence and logistics presentation (link on left). 
 
March 7, 2016
·    Taft drawings have been approved - they will be going out to bid ASAP.
·    Gym wall padding will be going out to bid shortly.
·    Field lighting review is almost complete.
·    Phase 1 HS/MS drawings have been approved and will be going out to bid shortly.
 
 
February 8, 2016 
·       SED review time has improved – they have hired some additional A&E firms.
·        Drawings for Taft boilers have been submitted to SED.
·        The construction team (WCSD, Arris, Keystone) have reviewed drawings for the track and tennis courts – drawings will be going to SED shortly.
·     RH schematic design will be send to Arris this week.
·      BOE wanted public notification of the facilities that will not be available this summer – as a timeline is established notification will be on the district website and various other locations.  
 
 
January 19, 2016 
·        Review Pre Referendum Master Summary Schedule
·        Impact of  Current SED Review Time on Schedule
·        Project Priorities
           * Implementation of Full Day Kindergarten
          * Mechanical and Electrical Replacement/Upgrades 
   *Modular Classroom Replacement at Elementary Schools 
      *Infrastructure 
·        Architectural Review 16 weeks 
·        MEP Review is 42-44 weeks 
·        Impacts to the Project 
       *Bidding Contract Award Time is pushed into late Spring/Early Summer 
     *Reduces available contractors 
         - Increases Costs 
       *Eliminates time for procurement and material long lead items 
·        Rearrange schedule to maintain District Goals 
   *Prioritize Round Hill Elementary 
    *Maintains Contract Award in Spring 2017 and Contract Completion in December 2018 
   *Little Britain Contract Award in Summer 2017 and Contract Completion in Summer 2018 
   *Taft Elementary Contract Completion remains Summer 2019 
   *WMS Infrastructure Contract Award in early 2018 and Contract Completion in Summer 2018 
    * WHS will still be completed over two summers in 2018 and 2019
 